楼顶防水有哪些注意事项
楼顶防水工程怎么做?看了这个实例示范就非常清楚了!本工程为住宅工程,楼顶防水工程为3厚SBS自粘聚合物改性沥青聚酯胎体防水卷材两道;40厚C20细石混凝土保护层内配Φ6@150双向钢筋。
How to do the roof waterproof project? After reading this example, the demonstration is very clear! The project is a residential project, and the roof waterproof project is two layers of 3-thick SBS self-adhesive polymer modified asphalt polyester matrix waterproof coiled materials; 40 thick C20 fine aggregate concrete protective layer, internal distribution Φ 6@150 Two way reinforcement.
楼顶防水工序与步骤楼顶防水工程的详细示范简直是手把手演示楼顶防水样板策划根据屋面工程作法确定样板施工样式,屋面排水坡度,画出屋面策划示意图。本建筑物总长33.56米,总宽度13.34米,总体南北向排水,坡度2%,东西向排水坡度1%,屋面共设排水口4只,其中北侧两只为侧排雨落水口,南侧两只下排雨落水口。
The detailed demonstration of roof waterproof process and steps is simply a hand-in-hand demonstration of roof waterproof model planning. Determine the model construction style and roof drainage slope according to the roof engineering practice, and draw the schematic diagram of roof planning. The building has a total length of 33.56m and a total width of 13.34m. The overall north-south drainage slope is 2% and the East-West drainage slope is 1%. There are 4 drainage outlets on the roof, including two side drainage outlets on the north and two lower drainage outlets on the south.

屋面策划示意图屋面排水坡度示意详图· 材料进场四方验收材料进场经过甲方、监理、施工单位及供货商四方共同检查并验收合格。。
Schematic diagram of roof planning, schematic drawing of roof drainage slope · acceptance of materials entering the site. The materials entering the site have been jointly inspected and accepted by Party A, the supervisor, the construction unit and the supplier..